Charging Technology
What a charger can deliver — and what a site actually uses.
Nameplate ratings describe the most a charger could deliver. Site planning depends on what vehicles accept, how long they stay, and how many charge at once.
AC charging
Level 2 charging
Level 2 equipment supplies alternating current (AC) — commonly at 208 V in commercial three-phase buildings or 240 V in single-phase service. The vehicle's onboard charger converts AC to DC for the battery, so the vehicle, not the station, often sets the actual charging rate.
Circuit capacity and delivered power
Continuous charging loads are generally sized so the circuit is not loaded beyond 80% of its rating. A 40 A circuit therefore supports about 32 A of continuous charging. At 240 V that is roughly 7.7 kW; at 208 V roughly 6.7 kW. A vehicle with a smaller onboard charger will draw less regardless of the station rating. Confirm sizing requirements with a licensed electrician under the adopted electrical code.
Where Level 2 fits
Long dwell times — workplaces, overnight fleets, multifamily, hotels, and long-term parking. Load sharing lets several ports divide a fixed circuit or panel allocation, increasing ports without increasing peak demand.
Limitations and risks
- Too slow for short visits; a one-hour stop may deliver only a modest number of miles.
- Many ports still add up: 40 ports at 7 kW is 280 kW of potential load before management.
DC conversion
DC fast charging
DC fast chargers convert AC to DC inside the equipment and deliver it directly to the battery, bypassing the onboard charger. Power is governed by the charger rating, the vehicle's maximum acceptance, battery state of charge, and temperature.
Charging curves
Most vehicles accept peak power only within a band of state of charge, then taper as the battery fills. A 350 kW charger may average far less over a session, and many vehicles cannot accept that rate at all.
Infrastructure and operating requirements
DC equipment typically requires three-phase service at higher voltage, substantial conductors, often a dedicated transformer, and equipment pads. Power electronics generate heat and rely on cooling systems; liquid-cooled cables are common at higher power. Equipment, installation, maintenance, and networking costs are significantly higher than Level 2.
Limitations and risks
- Highly sensitive to utilization — fixed costs and demand charges accrue whether or not vehicles arrive.
- Reliability expectations are high; downtime is visible and costly.
kW vs. kWh
Charging power versus energy
| Term | Meaning |
|---|---|
| kW (power) | Rate of energy transfer at a moment. |
| kWh (energy) | Amount of energy delivered over time: kW × hours. |
| Nameplate rating | Maximum output a charger is designed for. |
| Delivered power | What the vehicle actually accepts at that moment — often less. |
| Session energy | kWh delivered during one session; set by vehicle need, not dwell alone. |
| Peak coincident demand | Highest combined load across all chargers (and the building) in the utility's demand interval. |
Assumptions: 7.2 kW port, 8-hour dwell, employee commute needs about 20 kWh.
Maximum possible energy = 7.2 kW × 8 h = 57.6 kWh Actual energy needed = 20 kWh Time actually charging = 20 ÷ 7.2 ≈ 2.8 h Port idle-but-occupied ≈ 5.2 h
The port is occupied all day but delivers about a third of its theoretical energy. Power sharing among several ports could serve the same need with less electrical capacity.
Illustrative only. Figures are assumptions chosen to show the method, not quotes, tariffs, or expected results.
Assumptions: 20 Level 2 ports at 7.2 kW; 12 vehicles start charging within the same 15-minute window.
Unmanaged coincident peak = 12 × 7.2 kW = 86.4 kW Managed cap example = 50 kW shared across active ports Average per vehicle = 50 ÷ 12 ≈ 4.2 kW (≈ 4.8 h to deliver 20 kWh)
All vehicles still receive their energy within an 8-hour dwell while peak demand falls by roughly 42%.
Illustrative only. Figures are assumptions chosen to show the method, not quotes, tariffs, or expected results.
Charging connectors and compatibility
In North America the commonly encountered connectors are SAE J1772 (AC Level 2), CCS1 (Combined Charging System, which adds DC pins to J1772), and the North American Charging Standard (NACS), standardized as SAE J3400, which carries both AC and DC. Many automakers have announced transitions toward J3400 ports, and adapters exist in both directions.
For a commercial site, the practical questions are which vehicles you expect to serve over the equipment's life, whether equipment can be fitted with multiple cable types or retrofitted, and how payment and network authentication work across vehicle brands.
Verify before relying on this: Connector adoption timelines, adapter compatibility, and any connector requirements tied to public funding programs change frequently. Confirm with current SAE publications, equipment manufacturer specifications, and the terms of any program you apply to.
Charger utilization
Utilization can be measured several ways, and they tell different stories:
- Time utilization — share of hours a port is occupied by a vehicle.
- Energy utilization — kWh delivered ÷ (rated kW × hours available).
- Session count — number of sessions per port per day.
- Revenue-producing utilization — share of time or energy that is actually billed or avoids a cost.
Assumptions: one 150 kW charger, 10 sessions/day, 30 kWh average per session.
Energy delivered/day = 10 × 30 = 300 kWh Theoretical maximum/day = 150 kW × 24 h = 3,600 kWh Energy utilization = 300 ÷ 3,600 ≈ 8.3%
Single-digit energy utilization is not unusual for fast charging; the economics depend on whether revenue at that throughput covers fixed and demand costs.
Illustrative only. Figures are assumptions chosen to show the method, not quotes, tariffs, or expected results.